Below is the tentative church construction schedule:
- Submit Civil Drawing to Orange Cty: November, 2006
- Submit Full Drawings to Orange Cty: December, 2006
- Drawings returned from Orange Cty: April, 2007
- Sitework to begin: January, 2007
- Construction to begin: August, 2007
- Walls up and roof by October, 2007
- Interior framing, electrical, plumbing and HVAC rough-in: November, 2007
- Drywall, trim, interior doors, painting: November, 2007
- Exterior painting: January, 2008
- Electrical, Plumbing, HVAC completed by February, 2008
- Parking lot, sod and landscaping completed by March, 2008